Over the next few weeks (weather pending), Kinsley Construction will be milling and resurfacing the streets listed below. During this time, we are kindly asking residents to avoid parking on the selected streets.
Street access will be limited during construction, however residents should expect minimal inconvenience. IF trash collection is unable to occur due to potentially damaging fresh paving, double collection will occur on the next regularly scheduled collection date.
TENTATIVE SCHEDULE
Monday 4/11 – Milling on Bunker Hill Circle and Nittany Court.
Tuesday 4/12 – Milling on Hoffheins Drive and Singer Road.
Wednesday 4/13 – Milling on Singer Road. Base repair on Nittany Court and Hoffheins Drive.
Thursday 4/14 – Milling on Singer Road and McCurley Drive. Base repair on Singer Road.
Friday 4/15 – Milling on Old Farm Lane. Base repair on Singer Road and Old Farm Lane.
Monday 4/18 – Milling on Sorrel Ridge Lane. Pave Bunker Hill Circle and Nittany Court.
Tuesday 4/19 – Pave Hoffheins and/or Singer Road. Base Repair on Sorrel Ridge Lane.
Wednesday 4/20 – Pave McCurrley Drive.
Thursday 4/21 – Pave Old Farm Lane and/or Sorrel Ridge Lane.
Friday 4/22 – Finish Hoffheins Drive or Old Farm Lane (if needed).